Prepared bySpatialis · Economics + Strategy
StagePreliminary business case
StatusDraft model · illustrative inputs
Options appraisal · CBA + MCA

Knocknashane,
Brennanstown Road

Living with Assistance campus, Dublin 18. Four delivery scenarios tested against five operating models, scored on cost‑benefit and multi‑criteria grounds. Change any input and every result updates.

DLRCC · ZONING OBJECTIVE A · SITE C.1.4 HA · 60 RESIDENT CONCEPT
Perspective
Placeholder
Every cost, income and benefit figure in this model is a placeholder to show how the engine behaves. Resident numbers, cluster mix and scenario definitions come from the July 2026 presentation and the October 2026 scoping note; method defaults (4% discount rate, 10% contingency, 12.5% fees, VAT rates) are carried over from the Nenagh Digital Hub CBA (Nov 2020) and need confirming. Each input is tagged with where it came from. Replace placeholders with figures from the QS, operators and the HSE before any result is reported.
01 · OPTIONS MATRIX

Scenario and operating model scores.

Each cell is one scenario delivered under one operating model. The large figure is the weighted MCA score out of 100; the financial-sustainability criterion is scored automatically from the benefit/cost ratio. Select a cell to open its cash flows.

02 · SELECTED OPTION

What-if adjustments apply to every cell in the matrix, so rankings shift with them. Reset them to zero for the base case.

Annual cash flows and cumulative discounted net position

BenefitsCostsCumulative discounted net

Multi-criteria assessment

Scores 1–5. Weights are shown as a share of the total.

Weighted score / 100

Sensitivity of NPV to key inputs

Each bar moves one input while holding the rest at their current values. Longer bars mark the inputs that most need firm figures from consultation.

Present value by line

03 · WHAT IS BUILT AND WHEN

Delivery programme by scenario.

Pick a construction start year for each element, or leave it unbuilt. Click a track to move the start. Hatched bars are construction; solid bars are operation. Year 1 is the first appraisal year.

04 · INPUTS

Assumptions, by source.

Source taken from a project document. Nenagh method default carried over from the 2020 CBA. Placeholder illustrative only, to be replaced through consultation.

05 · METHOD

How the scores are built.

The engine follows the structure of the Nenagh Digital Hub CBA: annual cash flows over the appraisal period, discounted to present value, compared as NPV and benefit/cost ratio, alongside a weighted multi-criteria assessment.

Two perspectives

Financial (owner) counts only the cash that reaches the landowner: build costs with VAT where it cannot be recovered, the operating costs the owner carries, and the income, rent, sale proceeds or grant it receives. The operating model changes this view the most.

Economic (society) counts real resource costs (build costs without VAT, full operating cost whoever carries it) against the value of the service and wider benefits. Transfers such as sale prices, rent, HSE funding and VAT are left out. Operating models move this view through operating efficiency, occupancy ramp and timing.

Calculation

  • Discount factor = 1 / (1 + r)n, with year 1 discounted one period, as in the Nenagh CBA.
  • NPV = PV benefits − PV costs. BCR = PV benefits ÷ PV costs.
  • Prices are real (constant) by default, which matches a real test discount rate. Switch to nominal in the appraisal inputs to apply inflation, and raise the discount rate to match.
  • Land: the site's current-use value is a cost in year 1 for every option, including do nothing, and comes back as residual value wherever the site is kept. Sale options receive it in the sale price. Without this, selling always looks better than retaining.
  • Residual value at the end of the horizon is straight-line on the build cost over the asset life you set.
  • MCA: each criterion blends a scenario score and an operating-model score by the blend you set. Financial sustainability is scored from the BCR bands.

Points to resolve

  • The scoping note gives a 60-resident concept (5 + 15 + 15 + 25). The presentation's parking slide works from c.51 residents. The model uses 60.
  • Capacity of the Knocknashane House pilot (scenario 2) is not stated in either document. It is a placeholder.
  • Confirm the test discount rate and appraisal period against the current Public Spending Code guidance before reporting. The Nenagh CBA used 4% over 20 years.
  • SLO 73 (Brennanstown Road) bears on planning scores for every build scenario; the road and entrance cost is a single placeholder line.

Inputs to collect through consultation

Input groupWho provides itUsed in
Gross floor areas, build and fit-out rates, site and road worksArchitect (Studio-MAC), quantity surveyorCapital cost, residual value, building running costs
Placement funding per resident by level of careHSE disability services; operatorsFinancial income; placement value proxy
Staffing ratios and cost per WTE by level of careOperators (e.g. those reviewed in the presentation)Operating cost in both perspectives
Lease rent per bed, management fee, sale valueOperators, approved housing bodies, valuerFinancial view of each operating model
Alternative placement cost, family and community benefitsHSE, published evaluationsEconomic benefits
Criterion weights and 1–5 scoresClient workshopMCA score in every cell

Project file

The whole model, including every input, scenario and score, is held as one project file. Copy it to keep a version or to start the next job from this one; paste a saved file and load it to restore. Your edits are also kept in this browser.